News
I-5 South Corridor Improvements - Construction Alert
August 20, 2015
FLORENCE AVENUE INTERCHANGE PROJECT Construction activity is ongoing on sound walls and retaining walls along the northbound and southbound I-5, between Orr & Day Road and the Florence Avenue Bridge. In addition, crews opened Dollison Drive at Studebaker Road to through traffic. Demolition activity of a portion of the Pioneer Boulevard has been completed. On Sunday, Aug. 23 crews will begin mobilizing equipment to conduct CIDH drilling at the Imperial Highway overcrossing. This work will be conducted from 8:30 p.m. Sunday, Aug. 23 to 6 a.m. Monday, Aug. 24. Daytime partial lane closures (one lane in each direction) will be ongoing on San Antonio Drive at I-5, Imperial Highway at I-5, and Pioneer Boulevard at I-5, may be in effect, weekdays (Monday through Friday) between 9 a.m. and 3 p.m. Work on Union Street, between San Antonio Drive and Paddison Avenue, is ongoing and will be underway for a few more weeks. Union Street is being widened, sidewalks will be reconstructed and the street will become a cul-de-sac adjacent to San Antonio Drive. Access for local residents will be maintained at all times. Construction activity is also ongoing with several sound walls along the northbound and southbound I-5. In addition, work continues on the frontage roads along the northbound I-5 (Adoree Street) and southbound I-5 (Southbound Frontage Road). ROSECRANS AVENUE & BLOOMFIELD AVENUE BRIDGE PROJECT The latest pile driving activity at Bloomfield Avenue was partially completed last week; this activity will resume in one to two weeks. The contractor anticipates pile driving activity will begin at the Rosecrans Avenue bridge in September. Please be advised this work may be loud and disruptive due to equipment noise, vibration and pounding relate to pile driving activity. CARMENITA ROAD INTERCHANGE PROJECT Daytime pile driving activity is underway to construct the new northbound I-5 Carmenita Road off-ramp and the retaining walls at the new Excelsior / Carmenita intersection. This work will take place weekdays (Monday through Friday) between 7 a.m. and 3 p.m. This activity will be ongoing at this location for approximately the next one to two weeks. Please be advised this work may be loud and disruptive due to equipment noise, vibration and pounding related to pile driving activity. As a result of the traffic shift onto the new Carmenita bridge, the traffic pattern at the intersection of Firestone Boulevard and Carmenita Road has been temporarily detoured; motorists exiting southbound I-5 at Carmenita will only be permitted to continue straight on Firestone. DISCLAIMER: Due to the dynamic nature of construction, please note that all dates and times are subject to change due to unforeseen operational factors or inclement weather. |
For information regarding upcoming closures, detours and other construction activity, be sure to check out the project Google map. This map will be updated in real time, with the latest information regarding project construction. Click the image below to view the map. |