I-5 Corridor Improvements SR-134 to Buena Vista Street
October 29, 2015
CONSTRUCTION ACTIVITIES
October 29 - November 6, 2015
Work will occur during daytime hours unless otherwise noted.
SR 134 to Magnolia Boulevard
Alameda Avenue: Construction of concrete bridge barriers.
Magnolia Boulevard to Buena Vista Street
Buena Vista Bridge (Winona Bridge): Installation of falsework on southbound side.
Buena Vista Railroad Bridge: Shoring work.
Buena Vista Ramps: Grading operation between the ramps.
Burbank Western Channel: Backfilling trench operations.
Empire Avenue: Jacking operation to finalize falsework (night work). Drilling piles (cast in drilled holes) for the underpass.
Victory Place Bridge: Pouring columns.
Railroad Retaining Wall: Installation of precast wall panels between Buena Vista Street and Hollywood Way.
Southbound I-5 Retaining Walls: Grading and drainage installation for the retaining wall between Buena Vista Street and Empire Avenue. Backfilling retaining wall between Empire Avenue and Burbank Boulevard.
Demolition: Demo work near the southbound I-5 Buena Vista Street on- and off-ramps.
Utility Work: Underground utility work at San Fernando Boulevard east of Grismer Avenue.
CLOSURES & DETOURS
October 29 - November 6, 2015
SR-134 to Magnolia Boulevard
+ Intermittent closures of the northbound I-5 Alameda Avenue off- and on-ramps from 7 a.m. to 3:30 p.m.
+ The detour for the one-mile segment of the Los Angeles River Bike Path has been temporary lifted.
Magnolia Boulevard to Buena Vista Street
+ Up to two lanes of southbound I-5 between Buena Vista Street and Empire Avenue will be closed from 9 p.m. to 6 a.m.
+ Southbound I-5 Burbank Boulevard off-ramp will be closed October 30 from 3 a.m. to 6 a.m.
+ Southbound I-5 Buena Vista off-ramp will be closed October 29 from 9 p.m. to 3 a.m.
UPCOMING CLOSURES
SR-134 to Magnolia Boulevard
The northbound I-5 Alameda Avenue on-ramp will be closed for 55 hours beginning, tentatively, November 18. More details to come.