Take Twice Daily to Relieve Congestion.

News

I-5 Corridor Improvements Between Orange County Line to the I-605

May 20, 2016

FLORENCE AVENUE INTERCHANGE PROJECT

The most recent pile driving activity adjacent to the Florence Avenue interchange along northbound I-5, just south of the Florence Avenue bridge, has been temporarily completed. Crews also completed the most recent operation driving test piles along the southbound I-5 Florence Avenue on-ramp.

Work is underway along Dollison Drive Orr and Day Road in Downey and Santa Fe Springs, to begin constructing cul-de-sacs and/or realigning streets adjacent to northbound and southbound I-5. To complete this work, construction fencing will be repositioned to allow adequate room for the work area.
 

Crews are working to form soundwalls along northbound and southbound I-5. Roadway excavation is underway behind k-rail and the construction fencing, along Mondon Avenue between Cecilia Street and Buell Street. Over the next few weeks crews will be pouring concrete for the new soundwall adjacent to southbound I-5. This work will be conducted weekdays (Monday through Friday) between 6:30 a.m. and 3 p.m. and will be ongoing for approximately the next two to three weeks.

Finally, work is ongoing on the Orr and Day railroad bridge, which runs perpendicular to I-5, underneath the freeway, south of Florence Avenue. 


IMPERIAL HIGHWAY & PIONEER BOULEVARD PROJECT

Crews have begun work on the detention basin on Adoree Street / Zeus Street; this work will include grading, excavation and removal of the sidewalk on Zeus Street. This work will be conducted during the daytime, Monday through Fridays, and is expected to be ongoing for approximately one month. 

Adoree Street and Frontage Road, have both been opened to through traffic between Imperial Highway and Norwalk Boulevard.


Crews have completed major construction of the retaining wall along Mondon Avenue, between Tina Street and Bayla Street. The contractor will return to the area at a later date to complete finishing work.

As crews work on Imperial Highway, Pioneer Boulevard and Norwalk Boulevard bridges at I-5, one lane in each direction will be closed on each street (at I-5) during the daytime.

Pioneer Boulevard will be subject to potential intermittent closures to through traffic underneath the I-5, on the following days: Thursday, May 26, Friday, May 27 or Tuesday, May 31, between 6:30 a.m. and 2:30 p.m. as crews perform work on the bridge

deck.  The closure area is shown on the map below in red, the detour route is highlighed in blue.

e

ROSECRANS AVENUE & BLOOMFIELD AVENUE BRIDGE PROJECT

Crews will close outside lanes along northbound and southbound I-5 from Rosecrans Avenue to Carmenita Road, nightly between 10 p.m. and 5 a.m., Monday, May 23 through Thursday, May 26. No detour route will be needed, as one lane will remain open at all times. These lane closures are needed as crews complete paving work along the freeway mainline.

CARMENITA ROAD INTERCHANGE PROJECT 

Crews will close outside lanes along northbound and southbound I-5 from Rosecrans Avenue to Alondra Boulevard, nightly between 10 p.m. and 5 a.m., Monday, May 23 through Thursday, May 26. In addition, crews will close the southbound I-5 Carmenita Road off-ramp and the southbound I-5 Rosecrans Avenue on-ramp, nightly between 7 p.m. and 5 a.m., Monday, May 23 through Friday, May 27. Motorists will be directed to use the freeway ramps at Valley View Avenue while these ramps are closed. These ramp closures will allow crews to conduct paving operations. For detailed information regarding this closures including alternate routes, please visit the project Google map


The temporary southbound I-5 on-ramp at Carmenita Road has closed permanently and the new on-ramp is expected to open later this year. In the interim, motorists will be directed to continue on Firestone Boulevard, turn left on Alondra Boulevard, then turn right on Valley View Avenue to access the southbound I-5 on-ramp. For detailed closure information, including recommended detour routes, please visit the

project Google map


The intersection of Excelsior Drive and Carmenita Road is closed temporarily, while the intersection is reconstructed to tie in with the new bridge. Also, the northbound I-5 Carmenita Road off-ramp has been temporarily reconfigured. Motorists that exit northbound I-5 at Carmenita Road will be directed to turn right on Excelsior Drive, left on Spring Avenue and left on Pumice Street to access Carmenita Road. Click the map below for more information regarding the new off-ramp configuration. 


As a result of the traffic shift onto the new Carmenita Road bridge, the traffic pattern at the intersection of Firestone Boulevard and Carmenita Road has been temporarily detoured; motorists exiting southbound I-5 at Carmenita Road will only be permitted to continue straight on Firestone Boulevard.


DISCLAIMER: Due to the dynamic nature of construction, please note that all dates and times are subject to change due to unforeseen operational factors or inclement weather. 


← Return to News