I-5 Corridor Imrprovements Between Orange County Line to the I-605

February 3, 2017


Week of Feb. 5, 2017



FLORENCE AVENUE INTERCHANGE PROJECT

Drainage system installation and construction along Longworth Avenue between Harvest Avenue and Orr and Day Road (adjacent to northbound I-5), was scheduled to begin this week, weather permitting. Work will be conducted weekdays between 6:30 a.m. and 3:30 p.m. and is expected to take one to two weeks to complete.

Crews will be performing signal work at Florence Avenue and Orr and Day Road, intermittently over the next two weeks, weekdays between 9 a.m. and 3 p.m. This work will require lane reductions on Florence Avenue at Orr and Day Road; please expect delays and use an alternate route if possible. 

Pile driving operations are temporarily on hold along northbound I-5 at Florence Avenue and will resume in early 2017. 


In mid- to late-February (exact date TBD) the contractor will begin work to reconstruct the Florence Avenue bridge over I-5. The bridge will be reconstructed one half at a time, to accommodate the widening of I-5 below the bridge. To accomplish this work, Florence Avenue will be reduced to one lane in each direction between Orr and Day Road and Fairford Avenue, for approximately two years. The Florence Avenue on-ramp to northbound I-5 will also be closed during that time. The diagram below outlines the first stage of bridge construction (which will take approximately nine to 12 months to complete), including the temporary lane configuration, related ramp closures, and pedestrian access. To view all construction staging maps for Florence Avenue, visit the project website.

Click image to download as PDF.


Heavy traffic and delays are expected in the area surrounding Florence Avenue at I-5 once this work begins; motorists are urged to use alternative routes whenever possible. To view all alternative route maps, visit the project website.

Click image to view maps on project website.


Additional information, including the date the contractor plans to start this work, will be widely publicized as soon as it becomes available.


IMPERIAL HIGHWAY & PIONEER BOULEVARD PROJECT

As crews work on Imperial Highway, Norwalk Boulevard and Pioneer Boulevard bridges at I-5, one lane in each direction will be closed on each street (at I-5) during the daytime, between 8 a.m. and 3 p.m.


ROSECRANS AVENUE & BLOOMFIELD AVENUE BRIDGE PROJECT

Rosecrans Avenue will be closed to all through traffic (motorists and pedestrians) in both directions underneath I-5, Monday, Feb. 6 through Friday, Feb. 10 between 9 p.m. and 5 a.m. These closures are needed as crews remove falsework from the Rosecrans Avenue bridge. Nighttime closures on Rosecrans Avenue will continue intermittently for the next six months. For detour information visit the project Google Map.


In the coming weeks, crews plan to close N. Firestone Boulevard from Rosecrans Avenue to Bloomfield / Markdale Avenue, for approximately six months. An exact start date for this closure has not been set, but will be widely publicized once the work is scheduled. The closure area is shown in red on the map below; additional information, including detailed detour routes will be provided once the work is scheduled.

Pile driving activity adjacent to northbound I-5 near Rosecrans Avenue, will resume the week of Feb. 12, Monday through Friday between 7 a.m. and 3:30 p.m. Please be advised that pile driving work may be loud and disruptive due to equipment noise, vibration and pounding related to this operation. When this work is underway, flaggers will be on site to direct traffic, while crews transfer piles from the contractor's yard onto the construction site.  

CARMENITA ROAD INTERCHANGE PROJECT

Nightly lane reductions are planned on I-5 at Carmenita Road (one northbound lane and one southbound lane), Monday through Friday, between 10 p.m. and 5 a.m. These lane closures are needed for electrical work and clean up.

Electrical work along the shoulders of the northbound and southbound I-5 freeway at Carmenita Road is ongoing. This work will take place Monday through Friday between 7 a.m. and 4 p.m.

In addition to this work, landscape and irrigation work is ongoing along Frontage Road, N. Firestone Boulevard and S. Firestone Boulevard. This work will take place Monday through Friday between 7 a.m. and 4 p.m.

VALLEY VIEW AVENUE INTERCHANGE PROJECT

Crews are demolishing one half of the Valley View Ave. bridge at I-5 and removing footings and columns on the freeway. This work will require the full closure of the northbound and southbound I-5 freeway, between Artesia Boulevard and Carmenita Avenue. Access to I-5 from the westbound SR-91 and southbound I-605 will also be closed. Specific closure times and recommended detour routes are outlined below; additional information will be provided on the project Google map.

  • Northbound I-5 will be closed:
    • from 11 p.m. Monday, Feb. 6 to 5 a.m. on Tuesday, Feb. 7
    • from 11 p.m. Thursday, Feb. 9 to 5 a.m. Friday, Feb. 10
    • from 11 p.m. Monday, Feb. 13 to 5 a.m. Tuesday, Feb. 14

DETOUR (shown on map below in blue): Exit at Valley View Ave., right on Firestone Blvd., left on Trojan Way, left on Alondra Blvd., left on Freeway Dr. to access northbound I-5 on-ramp.

  • Southbound I-5 will be closed:
    • from midnight to 5 a.m. on Tuesday, Feb. 7
    • from midnight to 5 a.m. on Wednesday, Feb. 8
    • from midnight to 5 a.m. on Thursday, Feb 9

DETOUR (shown on map below in green): Exit at Carmenita Rd., right on Carmenita, left on Artesia Blvd. to access southbound I-5 on-ramp. 

  • Westbound SR-91 connector to northbound I-5 closed: 
    • from 11 p.m. Monday, Feb. 6 to 5 a.m. Tuesday, Feb. 7 
    • from 11 p.m. Thursday, Feb. 9 to 5 a.m. Friday, Feb. 10
    • from 11 p.m. Monday, Feb. 13 to 5 a.m. Tuesday, Feb. 14

DETOUR: Motorists will be directed to continue on westbound SR-91, transition onto northbound I-605, then to northbound I-5.

  • Southbound I-605 connector to southbound I-5 closed:
    • from 10 p.m. Monday, Feb. 6 to 5 a.m. Tuesday, Feb. 7
    • from 10 p.m. Tuesday, Feb. 7 to 5 a.m. Wednesday, Feb. 8
    • from 10 p.m. Wednesday, Feb. 8 to 5 a.m. Thursday, Feb. 9

DETOUR: Motorists will be directed to continue on southbound I-605, transition onto eastbound SR-91, then to southbound I-5.


Crews have closed the southbound Valley View Avenue off-ramp and reduced lanes (one lane in each direction) on the Valley View Avenue bridge over I-5. The duration of the ramp closure and lane reduction will be approximately two years. Heavy traffic and delays in the area are expected. If possible use alternate routes (shown on the map below). Portable changeable message signs have been placed in the vicinity to notify the motoring public.

Click map to view more information.


The contractor will be clearing and grubbing vegetation along the northbound I-5 Valley View on-ramp, weekdays between the hours of 7 a.m. and 3:30 p.m.


Crews will be removing asphalt between Arbor Place and Park Place, weekdays between 7 a.m. and 3:30 p.m.

Multiple utility relocations are ongoing throughout the construction site. There will be intermittent lane reductions on both N. Firestone Boulevard and S. Firestone Boulevard. Work will be performed Monday through Friday. 

A portion of S. Firestone Boulevard at Coyote Creek channel is now closed forutility relocation for a period of four to six months. Work will be conducted weekdays between 6 a.m. and 4 p.m. Businesses along Firestone Boulevard will remain open and detour signs will be posted. For detour information visit the project Google map.


DISCLAIMER: Due to the dynamic nature of construction, please note that all dates and times are subject to change due to unforeseen operational factors or inclement weather.

Also be advised that construction work may be noisy due to construction equipment, truck back-up alarms, and other construction related noise.



For information regarding upcoming closures, detours and other construction activity, be sure to check out the project Google map. This map will be updated in real time, with the latest information regarding project construction. Click the image below to view the map.