I-5 Corridor Improvements Between Orange County Line to the I-605

March 10, 2017


Week of March 12, 2017



FLORENCE AVENUE INTERCHANGE PROJECT

Crews are drilling CIDH piles for the Orr and Day railroad bridge, on the freeway. This work will be ongoing for approximately three weeks and will be conducted during the daytime. 

Florence Avenue Bridge Nighttime Lane Closures at I-5

Florence Avenue may be closed to traffic between Studebaker Road and Orr and Day Road, intermittently between 9 p.m. and 5 a.m. over the next week. 

Heavy traffic and delays are expected in the area surrounding Florence Avenue at I-5; motorists are urged to use alternative routes whenever possible.  

Click map to print.


Florence Avenue Bridge Lane Reduction at I-5 Beginning Monday, March 6

Florence Avenue bridge at I-5 (between Orr and Day Road and Fairford Avenue) has been reduced to one lane in each direction. The Florence Avenue on-ramp to northbound I-5 has also been close for approximately two years. The Florence Avenue bridge is being reconstructed one half at a time to accommodate the widening of I-5 below the bridge. 


The diagram below outlines the first stage of bridge construction (which will take approximately nine to 12 months to complete), including the temporary lane configuration, related ramp closures, and pedestrian access. To view all construction staging maps for Florence Avenue, visit the project website.

Click to view all staging maps.


Florence Avenue Nighttime Bridge Demolition at I-5

Crews have completed the first portion of nighttime bridge demolition activities on Florence Avenue bridge at I-5. Nighttime bridge demolition activities will resume in one to two weeks. Please note, this work will require nighttime full closures on northbound and southbound I-5. Closure information will be provided once the work is scheduled. 

IMPERIAL HIGHWAY & PIONEER BOULEVARD PROJECT

The northbound I-5 on-ramp at Imperial Highway has closed 12 months. Motorists are directed to use the northbound I-605 on-ramp at Firestone Boulevard, then transition back onto northbound I-5, as an alternate while the northbound I-5 Imperial Highway on-ramp is closed. The closure area is shown in red on the map below; the detour route is shown in green


Pile driving activity is underway adjacent to the northbound I-5 near Imperial Highway and will be ongoing for approximately the next six weeks. This work will be conducted intermittently, Monday through Fridays between 7 a.m. and 3:30 p.m. Please be advised that pile driving work may be loud and disruptive due to equipment noise, vibration and pounding related to this operation.

As crews work on Imperial Highway, Norwalk Boulevard and Pioneer Boulevard bridges at I-5, one lane in each direction will be closed on each street (at I-5) during the daytime, between 8 a.m. and 3 p.m.

ROSECRANS AVENUE & BLOOMFIELD AVENUE BRIDGE PROJECT

At 9 p.m. on Friday, March 10, crews plan to close N. Firestone Blvd. from Rosecrans Avenue to Bloomfield / Markdale Avenue, for approximately six months. This closure is needed as crews reconstruct N. Firestone Blvd., complete pile driving adjacent to I-5 and complete soundwall construction. The closure area is shown in red on the map below; the detour map is shown in green. 



Rosecrans Avenue may be closed to all through traffic (motorists and pedestrians) in both directions underneath I-5, Monday through Fridays between 9 p.m. and 5 a.m.
 Nighttime closures on Rosecrans Avenue will continue intermittently for the next six months. For detour information visit the project Google Map.


Pile driving activity adjacent to northbound I-5 near Rosecrans Avenue, will resume on Wednesday, March 15 and will be ongoing for one to two weeks. This work will be conducted intermittently, Monday through Fridays between 7 a.m. and 3:30 p.m. Please be advised that pile driving work may be loud and disruptive due to equipment noise, vibration and pounding related to this operation. When this work is underway, flaggers will be on site to direct traffic, while crews transfer piles from the contractor's yard onto the construction site.  

CARMENITA ROAD INTERCHANGE PROJECT

Landscape and irrigation work is ongoing along Frontage Road, N. Firestone Boulevard and S. Firestone Boulevard. This work will take place Monday through Friday between 7 a.m. and 4 p.m.

VALLEY VIEW AVENUE INTERCHANGE PROJECT

The northbound I-5 on-ramp at Freeway Drive is set to close permanently mid to late-March. Portable changeable message signs will be placed in the area two weeks in advance of the closure. Once this ramp closes, motorists will be detoured to proceed west on Alondra Boulevard, then north on Carmenita Road to access the northbound I-5 on-ramp. Heavy traffic and delays in the area are expected. Motorists are urged to use alternative routes whenever possible.  The closure area is shown in red on the map below; the detour route is shown in green. 


Freeway Drive under the Valley View bridge has been closed to through traffic and clearing and grubbing operations are ongoing.

On Thursday, March 16 crews will conduct pile driving activities along Valley View Avenue, adjacent to I-5. Please be advised that pile driving work may be loud and disruptive due to equipment noise, vibration and pounding.


Crews will be removing asphalt between Arbor Place and Park Place, weekdays between 7 a.m. and 3:30 p.m.

Multiple utility relocations are ongoing throughout the construction site. There will be intermittent lane reductions on both N. Firestone Boulevard and S. Firestone Boulevard. Work will be performed Monday through Friday. 

A portion of S. Firestone Boulevard at Coyote Creek channel is now closed for utility relocation for a period of four to six months. Work will be conducted weekdays between 6 a.m. and 4 p.m. Businesses along Firestone Boulevard will remain open and detour signs will be posted. For detour information visit the project Google map.


*DISCLAIMER: Due to the dynamic nature of construction, please note that all dates and times are subject to change due to unforeseen operational factors or inclement weather.



For information regarding upcoming closures, detours and other construction activity, be sure to check out the project Google map. This map will be updated in real time, with the latest information regarding project construction. Click the image below to view the map.