SR-134 to Buena Vista Street Construction Activities - Oct. 25-30, 2015
October 23, 2015
October 25-30, 2015 Work will occur during daytime hours unless otherwise noted. SR 134 to Magnolia Boulevard Alameda Avenue: Construction of concrete bridge barriers. Magnolia Boulevard to Buena Vista Street Buena Vista Bridge (Winona Bridge): Installation of falsework on southbound side. Buena Vista Railroad Bridge: Shoring work.
Empire Avenue: Jacking operation to finalize falsework (night work). Victory Place Bridge: Forming pile caps. Railroad Retaining Wall: Installation of precast wall panels between Buena Vista Street and Hollywood Way. Southbound I-5 Retaining Walls: Grading and drainage installation for retaining wall between Buena Vista Street and Empire Avenue. Backfilling retaining wall between Empire Avenue and Burbank Boulevard. Demolition: Demo work near the southbound I-5 Buena Vista Street on- and off-ramps. Utility Work: Underground utility work at North Keystone Street and Empire Avenue, and San Fernando Boulevard east of Grismer Avenue. |
October 25-30, 2015 SR-134 to Magnolia Boulevard + Intermittent closures of the northbound I-5 Alameda Avenue off- and on-ramps from 7 a.m. to 3:30 p.m. + Through October 2017, a one-mile segment of the Los Angeles River Bike Path will be closed between Riverside Drive and just south of the SR-134 overcrossing in the City of Los Angeles. For more information and the bike path detour, click here. Magnolia Boulevard to Buena Vista Street + Up to two lanes of southbound I-5 between Buena Vista Street and Empire Avenue will be closed the nights of October 25-30 from 9 p.m. to 6 a.m. + One lane of southbound Buena Vista Street may be closed intermittently October 26 and 27 from 7 a.m. to 3 p.m. Flaggers will direct motorists. For more information, click here. |