News
I-5 Corridor Improvements SR-134 to Buena Vista Street
September 23, 2016
PROVIDENCIA BRIDGE WORK: Through October, crews will be erecting and bolting girders to the Providencia Avenue bridge in Burbank. The work will require night closures of Flower Street and lane closures on I-5. Click here for more information. Construction activities and closures are subject to change. Please remember, illegal dumping is a crime. Violators will be prosecuted. |
Work will occur during daytime hours unless otherwise noted. SR-134 to Magnolia Boulevard Providencia Avenue Bridge: Erect and install girders (night work) on the southbound side of the bridge. Install falsework (wooden forms) for deck construction. More information is here. Los Angeles River Bridge: Removal of temporary supports (night work). I-5: Install concrete barriers between Providencia Avenue and SR-134 (night work). Magnolia Boulevard to Buena Vista Street Empire I-5 Undercrossing: Form and pour abutment walls. Buena Vista Street Bridge (Winona Bridge): Form center span. Strip falsework. Buena Vista Railroad Underpass: Waterproof steel deck. Form, pour and strip backwalls. Construct approaches (bridge ends). Empire Avenue Railroad Underpass: Erect steel bridge. Empire Avenue: Backfill retaining walls. Hollywood Way to Buena Vista Street: Place railroad ballast (rock). Form, pour and strip retaining wall coping (place cap piece on the wall). Victory Place Undercrossing: Strip falsework. Victory Place: Remove pavement. Install shoring. Burbank Western Channel: Place deck panels and form abutment. Click here for more information. Soundwalls: Remove existing block soundwalls between Empire Avenue and Cohasset Street. Old Front Street: Excavate and break out retaining wall. Pump Building: Mechanical work. Install drain for vault floor. |
SR-134 to Magnolia Boulevard Closures will be in place Sept. 26-30 unless otherwise specified. + Flower Street closed between Alameda Avenue and Verdugo Avenue the nights of Sept. 28 and 29 from 9 p.m. to 6 a.m. Detour posted. More information is here. + Southbound I-5 Verdugo Avenue on-ramp closed from 9 p.m. to 6 a.m., Sept. 23-30. + Through mid-2017 there will be intermittent daytime bike path closures between Riverside Drive and just south of the SR-134 overcrossing in the City of Los Angeles. When the path is closed, a signed detour will direct users to Zoo Drive and Western Heritage Way. See map here. Magnolia Boulevard to Buena Vista Street Closures will be in place Sept. 22-30 unless otherwise specified. + Up to two lanes closed on northbound I-5 between Burbank Boulevard and Buena Vista Street on Sept. 22. from 9 p.m. to 6 a.m. + Full closure of Empire Avenue between Wilson Avenue and Victory Place through November 2016. Work hours will be from 6 a.m. to 4 p.m., primarily Monday through Friday. The closure will remain in place 24/7. A detour will be posted. Click here for more information. + Intermittent nighttime lane closures on southbound I-5 between Hollywood Way and Burbank Boulevard. + Intermittent nighttime ramp closures at southbound Buena Vista Street off-ramp and southbound Burbank Boulevard off-ramp. + Buena Vista Street closures between Winona Avenue and San Fernando Boulevard:
|